Conditioning stations | |||||
No. | Year | Facility | Project | Scope | Status |
1. | 2023 | Łąkowa CHP Plant in Grudziądz | Development of high-efficiency cogeneration by constructing a biomass boiler unit at the Łąkowa CHP Plant in Grudziądz | Supply of a lance desuperheater with hydraulic atomization nozzles and a DN700 cooling chamber, including shut-off valves | In progress |
2. | 2023 | TAMEH Polska Sp. z o.o. Nowa Generation Plant | Modernization of SRS-14 | Design and execution in the technology, I&C, and electrical sectors; supply and installation of a conditioning station with shut-off valves and safety valves; I&C and electrical deliveries and installations; system work execution; commissioning participation; operator training | In progress |
3. | 2023 | TAURON Generation S.A. – Nowe Jaworzno Power Plant Branch | Emergency reconstruction of conditioning station A0LBA30 for the 910MW unit at TAURON Generation S.A. – Nowe Jaworzno Power Plant Branch | Valve seat redesign, supply and installation of the seat in the station, design of tee fitting installations in bypass pipelines, and gate valves; I&C and electrical installations; control algorithm update; regulatory valve modernization; drive setting; commissioning; optimization; operator training | In progress |
4. | 2022-2023 | EC Anwil S.A. | Modernization of TG4 turbine unit with the installation of a dedicated conditioning station | Comprehensive I&C, system, and electrical works and supplies; industrial valve (shut-off and control) supplies; I&C, electrical, and technological design execution | In progress |
5. | 2022-2023 | PGE GiEK S.A. Opole Power Plant Branch | Modernization of conditioning station RS1 on unit 4 at PGE GiEK S.A. Opole Power Plant Branch | Execution design, dismantling of the existing system with valves, supply and installation of control valves, station valve overhaul, necessary modifications in the existing reducing and cooling station | In progress |
6. | 2022 | PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Modernization of station 20SR supplying the 18 atm collector | Facility inventory, mechanical, electrical, and I&C design; complete station, valves, and instrumentation supply; dismantling, installation, commissioning, and handover for operation | Completed |
7. | 2022 | Grupa Azoty Zakłady Azotowe Kędzierzyn S.A. | Modernization of the 2.5 MPa steam reducing station in the Nitric Acid Plant of the Fertilizer Production Unit | Supply and installation of a 2.5/1.5 MPa steam reducing valve on the existing station with I&C and shut-off valves; supply and installation of a new 2.5 MPa/0.6 MPa steam reducing station; as-built documentation preparation | In progress |
8. | 2022 | Veolia Energia Łódź S.A. | Modernization of conditioning station SRS2 in EC-3 Veolia Energia Łódź S.A. | RS1 station reconstruction design, including UDT agreements, valve and electric drive inspection, replacement of strategic parts, supply and installation of new valves, I&C changes documentation | Completed |
9. | 2022 | Kraków Waste Incineration Plant | Supply of two conditioning stations with associated valves | Supply of two conditioning stations with associated valves | Completed |
10. | 2021-2022 | Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. District Heating Company | Design and modernization of the existing Municipal Heating Plant by constructing a high-efficiency cogeneration system using RES (biomass) | Supply of two conditioning stations with associated valves | Completed |
11. | 2021-2022 | TAURON Generation S.A. – Nowe Jaworzno Power Plant Branch | Modernization of the auxiliary steam system from Jaworzno II Power Plant to the unit collector for the 910 MW Unit | Design and comprehensive execution of two stations with associated valves, pipelines, injection water system equipped with 2×100% condensate pumps | Completed |
12. | 2021-2022 | EC Anwil S.A. | Construction of a 4.0/1.9 MPa conditioning station at EC Anwil S.A. | I&C design, control algorithm creation, supply of shut-off, check, control valves, conditioning station, safety valve, steam silencer downstream of the station, water silencer, injection water pumps, measurement nozzles; I&C and electrical installations; I&C, electrical, and system commissioning; operator training; as-built documentation preparation | Completed |
13. | 2020 – | JSW KOKS S.A – KKZ Division in Radlin | Construction of a coke oven gas-fired power unit at JSW KOKS KKZ – Radlin Coke Plant | Supply of three conditioning stations, installation guidelines issuance, control logic guidelines issuance, installation supervision, commissioning participation | In progress |
14. | 2020-2021 | EC Anwil S.A. | Construction of a 4.0 MPa steam pipeline from the CHP Plant (EC) to the Nitric Acid Plant (A-2) and installation of a reducing station at EC Anwil S.A. | Technological design (conditioning station design), I&C, electrical, and system design; industrial valve supply with drives and mechanical limit switches; I&C and electrical installations; system commissioning; operator training | Completed |
15. | 2019-2020 | PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Installation of a steamdesuperheater for the heating unit B at Pomorzany Power Plant for PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Heating unit B modernization – design, supplies, dismantling, installations, inspections, collision resolution, installation supervision, functional testing, and acceptance documentation for the steam desuperheater for the heating unit B and dedicated pipelines for discharging the steam-air mixture from heating exchangers XP1-XP4 to the turbine gland steam collector for units A and B | Completed |
16. | 2018-2020 | CEZ SKAWINA S.A. | Installation of a conditioning station (RS) intended to supply the WO-4 heating exchangers and the technological steam collector with superheated steam | Design work execution, valve and instrumentation supply, I&C and electrical installation work, commissioning participation | Completed |
17. | 2018-2020 | Tameh Polska Sp. Z o.o. ZW Kraków | Construction of a steam turbine unit with auxiliary systems at ZW Kraków | Design and supply of an SRS start-up and dump station and design and supply of a conditioning station operating in an automatic pressure and temperature control system for reduced steam at 0.8MPa(g) in place of the existing URO 2B station | Completed |
Specialized Installations for the Energy Sector (Drums, Bypass Systems for Regenerative Heaters, etc.) | |||||
No. | Year | Facility | Project | Scope | Status |
1. | 2022-2023 | PGE GiEK S.A. Dolna Odra Power Plant Branch | Installation of a Start-up Station for PGE GiEK S.A. Dolna Odra Power Plant Branch | Comprehensive design, manufacturing (including obtaining necessary permits), installation, commissioning, and handover of a complete Start-up Station with auxiliary installations. | In progress |
2. | 2022-2023 | ZE PKN ORLEN S.A. in Płocku | Modernization of high-pressure steam pipelines 13.6MPa/540°C at ZE PKN ORLEN S.A. in Płock | Delivery, dismantling, and installation of elements in the electrical and I&C sectors including DCS, required tests, participation in commissioning and final acceptance. | In progress |
3. | 2022-2023 | ENEA Wytwarzanie Sp. z o.o. | Installation of a connection system for technological steam collectors of units 1-10 with the steam collector of unit 11, including necessary facilities and installations based on a technological concept | Design in technological, mechanical, construction, electrical, and I&C sectors; I&C, electrical, construction works and supplies; mechanical works and supplies (supply of columns and KER supports, installation of newly designed trestle columns, pipeline installation and welding, pipeline insulation); valve supplies and installations. | In progress |
4. | 2022-2023 | Wrocław Combined Heat and Power Plant KOGENERACJA S.A. | Replacement of selected actuators on unit BC-2 and BC-3 at EC Wrocław | Design, selection, supply, dismantling, and installation of electric actuators; system adaptation works; commissioning works; functional tests and optimization. | In progress |
5. | 2022 | Veolia Energia Poznań S.A. | Modernization of the feedwater system for preheaters 10LAD10 and 10LAD20 | Supply and installation of control and shut-off valves, I&C, system work execution. | Completed |
6. | 2022 | Veolia Energia Poznań S.A. | Automation of the desalination process for boiler BK100 | Concept development for desalination modernization on boiler BK100; execution design with I&C design; modernization implementation on-site with connection to DCS; testing and commissioning of the modernized desalination system; as-built documentation preparation. | Completed |
7. | 2022 | ENEA Wytwarzanie Sp. z o.o. | Modernization of the level measurement system in the boiler drum of unit 10 at Enea Wytwarzanie sp. z o.o. | Documentation in technological, mechanical, and I&C sectors; supply of 3 complete measuring columns with radar transmitters and all necessary elements and devices for task realization; dismantling and installation works; commissioning of measurement systems. | Completed |
8. | 2021 – | Synthos Dwory 7 Sp. z o.o. | Supply, installation, and commissioning of a waste heat boiler and installation of a gas turbine set | Execution of facility inventory and expertise, HAZOP and SIL analysis, technological and mechanical, architectural and construction, and installation-engineering design. | In progress |
9. | 2021-2022 | Enea Połaniec S.A. | 200+ Program: Innovative technology for changing the operating regime of 200MWe class power units for the project on unit 4 at Połaniec Power Plant | Execution and as-built design of the transformer and inverter power supply; supply and installation of transformer and inverter; participation in commissioning; supply of manual and electric shut-off valves. | Completed |
10. | 2021 | PGE GiEK S.A. Dolna Odra Power Plant Branch | Overhaul of oil ignition stations and burners on boiler 8 at Dolna Odra Power Plant | Comprehensive rebuilding of the ignition station to adapt technical conditions to new valves; supply and replacement of all limit switches in the control system of igniters and oil burners; supply and replacement of parts for igniters and oil burners overhaul; verification of oil lances in terms of technical parameters; making all necessary corrections in control algorithms for oil burners and igniters; agreements with CLDT and UDT; optimization of the operation of oil burner systems within the overhaul; conducting tests with CLDT and UDT inspectors. | Completed |
11. | 2021 | PGE GiEK S.A. Opole Power Plant Branch | Overhaul of valves during the major overhaul of unit 4 at PGE GiEK S.A. Opole Power Plant Branch | Overhaul of control and shut-off valves on turbine extractions, steam extractions to turbine 1K12, ZZ1 feed, high-pressure regeneration XW, within RW2, within the 1.8 MPa and 0.4 MPa steam collector and RS-1, demineralized water, RW1 drainage expander, main condensate. | Completed |
12. | 2020-2021 | PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Restoration of the coal handling control room for PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Design of new power circuits for all receivers in the coal handling control room, including control and visualization systems; design in the system, fire protection, ICT, construction sectors; reconstruction of the existing room under the coal handling control room; installation of new power, lighting, air conditioning, telecommunication, sanitary systems; installation of a vision system. | Completed |
13. | 2020-2021 | EC Veolia Poznań | Modernization of PTWM180 boilers KW1 and KW2 | Turnkey execution including design, supply, dismantling and installation works, participation in commissioning, and acceptance of the power supply and automation systems. | Completed |
14. | 2020-2021 | PGE GiEK S.A. Turów Power Plant Branch | Restoration of oil burner systems on unit 6 for PGE GiEK S.A. Turów Power Plant Branch | Technical documentation of the boiler ignition system for the task, SIL calculations, dismantling existing systems and installations, supply and installation of new burner units, I&C apparatus, cooling and cleaning air systems with an independent compressed air source, control air system I&C, gas pipeline systems, pneumatic burner lance control systems, necessary system work, fire protection signal system adaptation, post-installation measurements of electrical and I&C installations. | Completed |
15. | 2020 – 2021 | Enea Połaniec S.A. | Supply of a heating station with a capacity of approx. 2 MWth for heating boiler water | Supply and installation of the heating station mounted on a steel frame. Scope: thermal-mechanical part (supply and installation of a shell-and-tube heat exchanger, electric drive control valves, additional valves), automation and electrical part (direct cable connections and signal paths to the control cabinet), construction part (installation of devices, mounts, pipeline suspensions, and control cabinet). | Completed |
16. | 2020 – 2021 | PGE GiEK S.A. Turów Power Plant Branch | Restoration of oil burner systems on unit 5 for PGE GiEK S.A. Turów Power Plant Branch | Technical documentation of the boiler ignition system for oil burner system restoration, SIL calculations, supply and installation of I&C apparatus, igniters with control boxes, gas and oil flame monitoring systems, shut-off valves for steam and oil, necessary system work, fire protection signal system adaptation, post-installation measurements of electrical and I&C systems. | Completed |
17. | 2020-2021 | Veolia Energia Poznań S.A. EC Karolin | Modernization of oil burners for PTWM 180 boilers | Design work (I&C with CLDT agreements and SIL analysis, electrical including modernization of existing switchboards for PTWM180 boilers, WP fan power supply), dismantling and installation in the I&C sector, participation in commissioning and acceptance. | Completed |
18. | 2020 | Wrocław Combined Heat and Power Plant KOGENERACJA S.A. | Replacement of balance flows in EC Czechnica and EC Wrocław | Replacement of heat meters on heating mains, legalization of heat meters on makeup water. | Completed |
19. | 2019-2020 | PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Overhaul of igniters and oil burners on boiler 6 for PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Unification project of igniter and oil burner drives, selection, supply, and replacement of actuators for igniters and oil lances, corrections in control algorithms, mechanical documentation. | Completed |
20. | 2019-2020 | PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Replacement of valves in auxiliary systems of unit 6 turbine set at PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Modernization of valves and pipework in carbon and alloy steel, including execution design in mechanical and I&C sectors with CLDT and UDT agreements, valve supply, I&C and electrical installation work, commissioning, testing, and optimization. | Completed |
21. | 2019-2020 | PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Medium expanded overhaul of unit 6 turbine set for PGE GiEK S.A. Dolna Odra Power Plant Complex Branch | Design documentation, electrical, I&C work, valve supply, commissioning, and optimization. | Completed |
22. | 2019 | Wrocław Combined Heat and Power Plant KOGENERACJA S.A. | Modernization of the water cooling system in CHP Wrocław | Technical design in all sectors, optimization of the injection water system, system work, valve supply. | Completed |
23. | 2019 | PGE GiEK S.A. Bełchatów Power Plant Branch | Modernization of the main steam pipelines of unit 2 at PGE GiEK S.A. Bełchatów Power Plant Branch | Overhaul of main DN300 steam valves, DN200 start-up valves, bypass valves, including repair technology development and UDT agreements. | Completed |
24. | 2018-2020 | Grupie Azoty Zakłady Chemiczne „Police” S.A. | Modernization of technological protections for OP230 boilers at Grupa Azoty Zakłady Chemiczne „Police” S.A. | Design documentation, CLDT and UDT agreements for designed solutions, implementation of designed lockout solutions, site work, testing, and technical acceptance. | Completed |
25. | 2018-2020 | PGE Energia Ciepła S.A. Pomorzany Power Plant | Construction of a semi-dry flue gas desulfurization installation and dry ash distribution system for two Benson OP-206 boilers | Design, supply, installation, implementation of control algorithms and communication with existing DCS system, DCS system software and commissioning, measurement tests and trials, participation in commissioning, quality and subcontractor documentation preparation. | Completed |
26. | 2018-2019 | Wrocław Combined Heat and Power Plant KOGENERACJA S.A. | Modernization of I&C equipment for WP120/K-3 boiler at EC Wrocław | I&C work execution and system modernization. | Completed |
27. | 2018-2019 | PGE GiEK S.A. Opole Power Plant Branch | Restoration of Ovation control and supervision system on units 1 and 2 and extension for new ignition burner and slag removal systems at PGE GiEK S.A. Opole Power Plant Branch | Transfer of control system for oil burners on units 1 and 2 from SIMATIC controllers to DCS OVATION; ignition burner and slag removal system installation work for units 1 and 2. | Completed |
28. | 2018-2019 | Orlen Południe S.A. Trzebinia Plant | Automation and visualization of existing CHP infrastructure with communication preparation for new DCS | Comprehensive task execution including technical documentation in all sectors, system work, I&C supply and installation, valve replacement, site instrumentation and automation system commissioning, integration with existing I&C systems. | Completed |
29. | 2018-2019 | Inowrocław Chemical Plants „Soda-Mątwy” | Comprehensive replacement of start-up valve systems including blowdown and emergency dump systems for K1-K4 OP110 boilers at EC Inowrocław | Multi-sector design of the new blowdown system from start-up and safety valves, valve replacement, verification of electrical and control installations per CSP standards, necessary control algorithm changes in DCS, system commissioning. | Completed |
30. | 2018 | PGE GiEK S.A. Dolna Odra Power Plant Branch | Overhaul of turbine and auxiliary equipment for unit 5 at Dolna Odra Power Plant | Supply of DN1600 PN10, DN1200 PN10 butterfly valves, AUMA gears, AMOT direct acting valve, degasser, coolers, and filters from Binko, installation of electrical and I&C systems, commissioning, and optimization. | Completed |
31. | 2017-2019 | ENEA Wytwarzanie Sp. z o.o. | Modernization of oil handling facility | Basic design (general, technological-structural, electrical, I&C, ICT), building, detailed, and as-built design; construction, technological, I&C, and electrical work; training; supplies. | Completed |
Industrial Installations (Steam Generators, Modernizations, Hydrogen Systems, etc.) | |||||
No. | Year | Facility | Project | Scope | Status |
1. | 2023 | ANWIL S.A. | Construction of a new peak-reserve steam source – KPŚ II at the ANWIL S.A. CHP Plant in Włocławek | Installation of a peak-reserve source producing steam at 4.0 MPa and a maximum net output of 50 Mg/h, and two sources producing steam at 0.8 MPa and a maximum net output of 50 Mg/h each. Scope includes: technological, construction, electrical, I&C, telecommunication, ventilation, water and sewage, and fire protection designs; supply and installation of three steam boilers with a net output of 50 Mg/h each, three feedwater tanks with deaerators, water treatment stations, feedwater pumps, expanders and condensate tanks; two reducing and cooling stations, three stations to ensure steam for each of the three boilers; I&C, electrical, and telecommunication supplies and installations. | In progress |
2. | 2022-2023 | Gaj Oławski | Construction of a high-efficiency trigeneration unit with a total nominal electric power of up to 1.0 MW | Design, execution, supply, and supervision over the installation and first commissioning of a hydrogen pressure reduction station with necessary valves, an independent hydrogen cooling/heating system separated from the cooling medium installation, and a buffer tank with a minimum capacity of 1.2m3/40bar. | In progress |
3. | 2022-2023 | PGE GiEK S.A. Rybnik Power Plant Branch | Design and construction (EPC) of a start-up boiler house with two steam generators for PGE GiEK S.A. Rybnik Power Plant Branch | Comprehensive design, construction, supply, installation, commissioning, and handover (turnkey) of a start-up boiler house with two identical steam generators, each with a net steam output of no less than 20 Mg/h, equipped with burners adapted to burn two fuels (light oil and natural gas). | In progress |
4. | 2022 | PGE GiEK S.A. Dolna Odra Power Plant Branch | Replacement of the hydrogen pipeline at PGE GiEK S.A. Dolna Odra Power Plant Branch | EPC task execution. Scope includes: technological, I&C, and electrical designs; mechanical, electrical, and I&C supplies and installations; supply and installation of valves; replacement of the electrolyzer generation module, HTA sensor; annual electrolyzer inspection. | In progress |
5. | 2021-2022 | PKN Orlen S.A. | Modernization of BMS on boilers K1-K7 at the CHP Plant in PKN Orlen S.A. | Determination of reference parameters for settlement during the trial run, technological analysis of co-firing possibilities on burners, combustion safety analysis, correction and setting of security settings, and alarm level determination, participation in CLDT agreements, preparation, and agreement of fuel pipeline cleaning procedure. | Completed |
6. | 2021 | Enea Połaniec S.A. | Heating of the recirculation system of the electrostatic precipitator for unit 4 | Supply and installation of measurement equipment on flue gas channels, steam, and condensate pipelines; supply of a heater, manual valves, and valves with actuators on steam and condensate pipelines; supply of an inverter and transformer; power supply to the flue gas recirculation fan, sealing air fan, shut-off and control actuators, and flow measurements from technological switchboards; cabling to the device control and measurement system. | Completed |
7. | 2020-2022 | TAURON Wytwarzanie S.A. – Łaziska Power Plant Branch | Construction of a pilot research installation as part of the project „Development of industrial construction of carbonate fuel cells and ceramic electrolyzers enabling integration with power-to-gas energy installations” | Comprehensive task execution. Scope includes: design documentation, obtaining required permits, supply and installation of SOE cells, MCFC cells, flue gas preparation nodes, compressed air preparation nodes, and gas preparation nodes for the CO2-SNG installation; integration of the supplied cell module with other nodes. | Completed |
8. | 2020 | PGE Energia Ciepła Branch No. 1 in Kraków | Concept development and design for the modernization of FSC technological protections on units 1, 2, 3, 4 at PGE Energia Ciepła Branch No. 1 in Kraków | Inventory of the existing state, concept development for the modernization of technological protections, agreement on conditions and scope of modernization with UDT, delivery of a complete modernization project agreed with UDT for units 1-4. | Completed |
9. | 2019-2021 | PGE GiEK S.A. Opole Power Plant Branch | Restoration of field instrumentation and automation system for the Wet Flue Gas Desulfurization System of units 1-4 at PGE GiEK S.A. Opole Power Plant Branch | Comprehensive task execution. Scope includes: I&C supplies and installations, supply and installation of control and regulation systems, system work execution, post-installation verification. | Completed |
10. | 2019 | ENEA Wytwarzanie Sp. z o.o. | Installation of a measurement system based on laser technology in an industrial design, applied in explosion hazard zones on boiler unit 6 | Comprehensive installation and commissioning. | Completed |